05 / INVENTORY & COSTING
Know what is in stock and what each job actually cost.
Follow materials through receiving, production and shipment. Compare actual material, labor and overhead with the estimate to explain the variance and improve the next quote.
- Estimated
- $4,400
- Actual
- $4,520
- Over estimate
- +$120
- Finished stock received
- 40 units
- Planned / actual cost per unit
- $110 / $113
- Over estimate per unit
- +$3
HOW IT WORKS
Inventory & Costing in three steps.
- STEP 01
Track stock by stage and location
Separate on-hand, reserved, available, incoming and work-in-progress quantities. Track item, location and lot where relevant.
- STEP 02
Assign costs as transactions happen
Post actual issues and production receipts. Include recorded labor and overhead when calculating the cost of the completed job.
- STEP 03
Explain the variance before the next quote
Compare planned and actual cost and review what changed: purchase price, material usage, labor time or scrap.
01 / STOCK AVAILABILITY
Separate what is on the shelf from what is free to promise.
Physical inventory, job reservations and quality holds answer different questions. Show the usable balance for the current job separately from the quantity already committed to another order.
- Finished assemblies received
- 40 units
- On quality hold
- 0 units
- Reserved for SO-1042
- −40 units
- Available for another order
- 0 units
All 40 units are physically in finished stock at this checkpoint, but none is free to promise to another customer.
02 / INVENTORY TRANSACTIONS
Follow the quantity from component issue to customer shipment.
Show the posting that changes the balance at each stage. A progress report can tell the planner what is happening, but does not itself move material into or out of stock.
- Material issue
Raw material → work in progress
Issue 40 seal kits, then one replacement; record the damaged kit against the job.
- Progress
Work in progress stays open
32 assembled units are an operational checkpoint, not a stock receipt.
- Production receipt
Work in progress → finished goods
Receive 40 cleared units after May 19 inspection.
- May 20
Finished goods → customer shipment
Ship the 40 units reserved for SO-1042.
Keep the lot and work-order references on the posted records. Correct errors with a traceable adjustment, not by rewriting the history.
03 / PLANNED VS ACTUAL
Reconcile every dollar of the $120 overrun.
Compare the same scope on both sides: 40 good pump assemblies under the same job. A component loss and extra labor changed actual cost even though shipment quantity stayed the same.
| Cost driver | Estimate | Actual | Variance |
|---|---|---|---|
| Materials | $3,120 | $3,180 | +$60 |
| Direct labor | $840 | $900 | +$60 |
| Machine & overhead | $440 | $440 | $0 |
| Total job cost | $4,400 | $4,520 | +$120 |
| Per good unit | $110 | $113 | +$3 |
Material increased by $60 for the replacement kit. Labor increased by two hours at $30 per hour, from 28 to 30 hours.
04 / VARIANCE REVIEW
Separate a one-off loss from a repeatable cost driver.
Investigate the events behind unfavorable variance before updating a standard or a quoting rate. The extra material and labor on this job are evidence to review, not automatic changes to every future estimate.
- +$60 · Material usage
One additional seal kit
Check the scrap posting and whether the damage points to a recurring handling problem.
- +$60 · Labor time
Two extra direct-labor hours
Review reported time and decide whether setup or run assumptions should change.
- $0 · Machine and overhead
No change in this example
Carry the original assumption forward unless the underlying rate or method has changed.
Keep the approved $4,400 baseline and the $4,520 actual visible after close so the reason for the difference is not lost.
05 / NEXT-QUOTE FEEDBACK
Use the closed job to improve the next estimate.
The original sales order stays at $150 per unit. Use closed-job history to review the next quote, and show how costs changed gross margin without rewriting the accepted price.
| At 40 units | Quote estimate | Closed-job result |
|---|---|---|
| Revenue | $6,000 | $6,000 |
| Job cost | $4,400 | $4,520 |
| Gross profit | $1,600 | $1,480 |
| Gross margin | 26.7% | 24.7% |
The estimated and actual margins are both based on this job’s cost and the same sales price. Keep the approved quote intact.
PUMP ASSEMBLY EXAMPLE
Carry the actual cost into the next quote.
The job closed at $4,520 compared with a $4,400 estimate. Across 40 units, that is $3 more per unit than planned.
Review material usage and labor time before changing a standard cost or quoting the next order.
THE HANDOFF
What goes in. What comes out.
- INPUTS
- Stock movements · Production output · Actual job costs
- OUTPUT
- Available stock, a closed job and a cost variance
COMMON QUESTIONS
Inventory & Costing FAQ
How is available stock different from on-hand stock?
On-hand is the physical balance. Available stock excludes quantities already reserved or unavailable for use.
How do I compare actual and quoted cost?
Compare posted material, labor and overhead with the estimate at the same quantity and scope. Review variances before updating reference costs for future quotes.
KEEP EXPLORING
Continue the manufacturing workflow.
PERSONALIZED WALKTHROUGH
See inventory & costing with your own data.
Bring the estimate and recorded costs for a completed job. Walk through what changed and what to use on the next quote.